Ready-to-build is a transaction description that needs documentary support. We help buyers and investors test the claimed development status of Romanian solar, wind and BESS projects and reflect the remaining work in the acquisition terms.
ON THIS PAGE
02
The seller says RTB. Can the documents support it?
The decision in front of you
An attractive project may still depend on unresolved land rights, permit conditions, grid works or changes to its configuration. Buying the label without testing the evidence can move development risk into your acquisition price.
Our response
A clear position. A practical next step.
We test the claimed ready-to-build stage against the land, permitting, grid and ANRE file. We then connect each material gap to a required action, completion condition or contractual protection, so you can negotiate on a documented basis.
03
What we do for you
We agree the depth of the review and the work needed for your decision. The scope can cover the following workstreams.
01
Define RTB for the actual project
Agree a document-based definition of the stage being purchased. The definition should fit the technology, site and connection configuration. A seller's RTB label is a starting point for investigation, rather than a conclusion about construction readiness.
02
Test land, permits and grid together
Review land rights and access, planning and construction documents, environmental requirements, the connection study, ATR and connection agreement. Check that they refer to the same site, capacity, technology and project company and identify amendments, challenges or unresolved conditions.
03
BESS needs configuration-specific diligence
For storage, the review should distinguish standalone and co-located arrangements, MW and MWh, import and export rights, operating assumptions and regulatory status. Technical and commercial specialists should test whether the proposed equipment and revenue assumptions fit the documented rights.
04
Convert gaps into acquisition terms
Use a maturity matrix showing the evidence, unresolved item, responsible party and required action. Link material gaps to conditions, milestone payments, price retention, warranties or specific indemnities. A target date should not substitute for an objective deliverable.
05
Report what remains to be done
The buyer needs to understand what is verified, what is conditional and what remains outside the review. Legal readiness, technical readiness, funding and construction mobilisation are connected but distinct decisions. The final report should make those boundaries explicit.
04
How we move your matter forward
From instruction to delivery
Clear responsibilities, a documented position and actions tied to the next decision.
01
Define the stage you are buying
We agree what RTB means for the technology, site and connection configuration.
02
Reconcile the project file
We test whether the documents cover the same SPV, location, capacity and intended installation.
03
Set the acquisition conditions
We identify which actions must precede payment or completion and reflect them in the deal documents.
05
Selected project experience
Anonymised examples of legal mandates. Client identities and commercial details are not disclosed.
Five-project RTB acquisition programme
Legal support for one client across a package of five Romanian energy projects, connecting the acquisition of project SPVs with the underlying development documents.
Our role MoU and SPA work, legal due diligence and coordination of project findings with the transaction documentation.
Legal support delivered An integrated legal workstream across the five-project package, bringing the commercial terms, project review and acquisition documents together.
Three-project SPV acquisition mandate
Legal support for a client pursuing three Romanian energy-project acquisitions through project SPVs.
Our role MoU and SPA work and legal due diligence across the acquisition programme, linking the review of each project to its transaction documents.
Legal support delivered Coordinated legal support across three acquisitions, maintaining a common approach to project review and transaction documentation while addressing each project's particular issues.
06
Start with the essentials
First conversation
Seller teaser and RTB definition
Land and access documents
Planning, environmental and construction file
ATR, study and connection agreement
Permits, ANRE status and project contracts
Begin with a non-confidential summary and your timetable. We agree the document exchange after checking conflicts and the scope of the mandate.
07
Questions before you instruct us
Does RTB guarantee a project can start construction immediately?
The label alone does not establish that. Readiness needs to be tested against the project's documents, conditions, configuration and remaining actions.
Can a BESS project use the same checklist as a solar project?
Some workstreams overlap, but storage configuration, import/export rights, operating assumptions and contracts need specific review.